Best way to make Subcontracting Job Work Order

What is Subcontracting Job Work Order?

“Subcontracting Job Work Order” is the Order that is agreed and issued to a Subcontractor with an agreed list of Products, Quantity and Unit Price to perform the subcontracting work and convert them to the needed finished goods.

Many Subcontractor’s will be negotiated very hard for the unit price for the Items and quantity that’s sent to them to work on. So Job Work Order is like a blanket order with an agreement between the Customer and Vendor that customer going to send minimum number of Quantities and vendor agreed for a fixed amount.

How Subcontracting Job Work Order helps?

So Customer would be using this Job Work Order as a reference to check the ODC and ensure that he sends the items as per the agreed terms. If the quantity sent exceeds the agreed quantity then ERP would stop the customer from sending more items and he has to renegotiate the unit price again. Or pay extra money as per the latest price points.

One Job Work can be used to make multiple Outward Delivery Challans (ODC). Each ODC can be used to make multiple Inward DCs or Multiple ODCs can be combined to make one IDC too.

Subcontracting Job Work Order Layout

Field Details of Job Work Order is as below

NoField IDField namemandatoryField description and how it helps?
1.Job work NumberJobwork IDYes It assigns a number to the particular job work order. It can also be entered manualy and create a new Jobwork Order.
2.Subcontractor IDSubcontractor IDYes It gives the unique Subcontractor identification number to each and every Subcontractor who is assigned the job work to be done.
3.Subcontractor NameName of the SubcontractorYes Name of the subcontractor to whom the job work is assigned to.
4.Credit Terms Terms of credit paymentYes It provides the duration for the payment to be made to the Subcontractor on receipt of Finished Goods.
5.Reference Reference No Any reference made to job work is mentioned in this section.
6.Order DateJobwork Order dateYes It gives the particular date on which the job work order was received by the subcontractor.
7.Due DateValidity of the Jobwork OrderYes Validity of this Jobwork Order. 
8.CurrencyDocument currencyYesCurrency code
9.Finished Goods IDFG IDYes FG ID
10.Description Finished Goods DescriptionYes FG name.
11.Service IDService ID of the work to be deliveredYes Service ID of the work to be delivered
12.UOMUnit of measurementYes UOM of the service as it connects to the Unit Price.
13.Quantity to DeliverTotal quantity to be delivered to Subcontractor.Yes It gives an agreement on the total Quantity that would be processed for the specific service ID and amount to pay.
14.Unit Sale Price of ServiceSale price of service for one unit of Finished GoodYes It gives the Unit Selling Price for single Finished Goods.
15.Total Cost Of FGTotal Cost of Finished GoodYes It gives us the total cost incurred for producing the total number of Finished Goods.
16.Shipping AddressAddress to be delivered to Yes It gives the destination address to where the Raw Material has to be delivered to.
17.Shipping ModeMode of DeliveryYes It gives the transportation mode by which the Raw Material will be delivered to the destination.Ex: By Air, Cargo etc.
18.Memo Memo Yes Any other comments to be added here for the contract related terms.
19.TOTALTotal amount Yes It provides the total amount charged for the job work done by the Subcontractor.

Important Note

  1. Subcontracting Job Work Order helps to simplify the process of creating Outward Delivery Challan and what items to send etc.
  2. This helps to stop creating ODC, when the Job Work Quantity is fulfilled.
  3. However this is not a mandatory to create ODC. Many customers, directly create an ODC and send the Materials to Subcontractor.